Planning
A step-by-step guide to site surveying, component selection, and creating your installation plan.
System Overview
Familiarize yourself with available mounting trims, prebuilt dot lengths, and accessories. Know how each component works together to build out the total system.
Dot Specifications
| System Voltage | 24V DC |
| Dot Quantities | 1, 5, 10, 25, 50, or 100 |
| Lead / Tail | 6" lead and 6" tail |
| String Spacing | 12" between dots |
| Channel Spacing | 9" between dots |
| Power Draw | 0.5W per dot |
| Max Run Length | 165 dots |
Aluminum mounting channel — field cuttable, 2 meter standard length, paintable surface with high-quality look and finish. Multiple solutions for every surface installation.
Basic Channel
Standard aluminum extrusion for flat surface mounting
Backer Channel
Recessed profile for flush façade integration
Chase Channel
Deep-set channel for concealed wire runs
45° Channel
Angled profile for soffit and eave installations
Flash Channel
Low-profile trim for tight clearance areas
Mounting Clips
Field-installed clips for flexible surface positioning
Planning Process
Follow these steps in sequence. Each builds on the previous to ensure an accurate quote, smooth install, and satisfied client.
Now that you’re familiar with our system (Step 1, above), make time to understand your client's goals for end appearance and clarify estimated cost of install based on these stated objectives.
Accurate measurements of each segment for all runs are a must for quoting and ordering of the required components accurately. This is a key step and must be completed before moving on in the process.
Based on the building’s design, equipment ground access, and client’s desired lighting design, identify any areas of concern.
-
Ground, roof, and interior site access need to be accounted for based on installer safety requirements related to seasonal conditions and positioning of install equipment around obstacles.
-
Not all buildings are constructed alike — based on customer’s desired install locations, additional planning may be required to mitigate specific façade or structural obstacles. Inspect these areas in advance and document as much information as possible.
-
Have a plan and communicate with the client regarding how you propose to solve obstacles prior to installation. List any additional tools or materials required.
Good planning is key to a successful install.
-
Plan out controller installation location based on power availability, user access, environmental conditions, and proximity to WiFi signal. Measure signal at proposed location to ensure good connectivity.
-
Take into account the direction of the data flow and animation direction along each run so that no segments are moving opposite to adjacent runs.
-
Document the length of each run to generate dot module totals, jumper cable lengths and quantities, linear feet of mounting trim, and any power injection components required.
-
Allow for a minimum of 10% waste on mounting trim ordered to account for centered segments, corner folding, and mis-cuts.
-
Order a few additional short dot segments (1’s and 5’s) and extra jumper cables to be prepared for unplanned issues.
Sample Installation Diagrams
Reference these layouts when creating your installation plan. Data flow direction and zone segmentation are shown for two common roofline configurations.
Sample A
Single-story roofline with two zones. Control box positioned at lower-right. Jumper cable bridges zones across the gable peak.
Sample B
Multi-peak roofline with independent zones along each ridge line. Control box at lower-right with separate zone routing.
Key Planning Specs
Reference numbers for successful installations
Max dot count before a 96W Driver is required
Exceeding this threshold requires an Auxiliary Box + T-con
Minimum waste buffer for corners, centered segments, and mis-cuts
9" spacing when dots are loaded into aluminum mounting channel
Bill of Materials Checklist
Use this reference when building your project quote and material order.
Dot Modules
Per-zone totals based on measured run lengths at 9" spacing in channel
Jumper Cables
Calculate required lengths and quantities between each run segment
Mounting Channel / Trim
Order with a minimum +10% overage for waste
Control Box
One per system — plan location near power and WiFi access
96W Driver + End Wire
Required if any run exceeds 165 dots
Auxiliary Box + T-con
Required if any run exceeds 330 dots
Short Dot Segments (1’s & 5’s)
Spares for unplanned field adjustments
Extra Jumper Cables
Order a few extra for unplanned routing changes